Releases from Omega West Reactor were
commonplace in the late
1950's and early 1960's, according to H-Division Monthly
Progress
Reports (Table, below). However, no reports in this series
later than
1964 have been released to the public. OWR operated until
leaks forced
its shutdown in 1992.
Incidents, Accidents and Ventings Related to Omega Reactor in H-
Division Progress Reports Prior to 1964
Date of H-Division
Progress Report Occurrence
3/21/62-4/20/62 "The
continuously recording gamma rate
meters indicated a few short time
rises, which correlate
with the Omega stack gas
activity."
1/21/62-2/20/62 "The
continuously recording gamma rate
meters indicated a few short time
rises, which correlate
with the Omega stack gas
activity. There has been no
noticeable increase due to
fallout."
9/20/61-10/20/61 "Beta-gamma
activity in air and
precipitation has been somewhat
higher. The average
figures are approximately five to
ten times the values found
during the summer months...
"The continuously recording gamma
rate meter showed a few
short time rises which
correlate with Omega stack gas
activity. There has been no
noticeable increase due to
fallout."
2/21/62-3/20/62"The continuously
recording gamma rate
meter showed a few short time
rises which correlate with
Omega stack gas activity. There
has been no noticeable
increase due to fallout."
12/21/61-1/20/62"The continuously
recording gamma rate
meter showed a few short time
rises which correlate with
Omega stack gas activity. There
has been no noticeable
increase due to fallout."
11/21/61-12/20/62"The
continuously recording gamma rate
meter showed a few short time
rises which correlate with
Omega stack gas activity. There
has been no noticeable
increase due to fallout."
8/20/61-9/20/61"The continuously
recording gamma rate
meters showed only a few short
time rises due to Omega
Stack gases. Any increase in
background due to Russian
weapon test fallout is not
noticeable."
7/20/61-8/20/61"Two fission gas
releases occurred at the
Omega West reactor during the
month."
12/20 60-1 20/61"An experiment in
which plutonium was
irradiated in the OWR was
started on January 23.
Difficulties developed in the
equipment which required a
shut down. Radiation levels on
the top of the reactor
reached 3 r/hr..."
9/20/60-10/20/60"On September 28
a plug broke while K-
Division was identifying the
different fission gases
produced by the OWR..."
"A purging of fission gases at
the Omega West reactor
showed up in pips on the area
monitors and in the air
samples taken on the
Administration Building roof."
4/20/60-5/20/60"On May 16 a power
run with Godiva took
place at TA-49 for approximately
6 hours. Many neutron
and gamma measurements were
made..."
3/20 60-4 20/60"Work on Kiwi A-3
fuel elements was
started by N-i at TA-46. Although
the building at this site
was not designed for work with
radioactive materials,
ventilation equipment was
installed which has kept the air-
borne activity in the work area
below the maximum
permissible level. ...the air-
borne activity discharged from
the stack has been high,
averaging between 2000 and 3000
d/m/M3."
12/20/59-1/20/60"The community
background monitors
have had a few short-lived pips
during the month. They
usually match conditions of
inversion in the atmosphere,
and seem to reflect TA-2
activities."
5/20/58-6/20/58"On May 27 at 2:52
p.m., a power
transformer in the Omega area
failed which caused a power
failure of the Omega Water
Boiler. An air sample taken in
the control room showed a count
of 3 mr/hr or
approximately 20 times tolerance.
The Water Boiler Section
of the building was evacuated and
all doors opened to flush
out the gases..." "On May 29 at
4:00 p.m. there was a
power failure at the Omega Water
Boiler caused by
overloading a circuit during
experiments. The conditions
were the same as above in
radiation levels at the area was
evacuated."
"On June 6 at 9:58 a.m. there
was a power failure at
Omega Water Boiler. Levels were
approximately 3-4
times tolerance and failure was
attributed to generator
failure..."
These are the latest H-Division Progress Reports
released to the public in the Human Studies Project Team's 31-
volume set of notebooks in 1994:
607. Shipman, T.L., H-Division Progress Report, July 21 -
August 20, 1963.
608. H-Division Progress Report, August 21, 1963 - September
20, 1963.
609. Shipman, T.L., H-Division Progress Report, December 21,
1963 - January 20,
1964.
Some are also available from DOE's OpenNet database.
However, none later than 1964 have been released to the
public.
Two issues in the late 1960's may be of particular public health
importance:
� the wattage of Omega West Reactor was increased from 5 to 8 MW.
Regulatory authorities raised serious concerns about emissions
of fission products, including radioiodine (See Question #17);
and
� emissions of plutonium from TA-21 increased in the months after
the fire at the Rocky Flats in May 1969 (See Question
#11).
The month-to-month narrative contained in the Health Division
Monthly Progress Report series may shed considerable light on
these issues in the late 1960's.
Home